Phase 03

Post-Production

Assembly through final delivery — cuts, revisions, finishing, and locked masters.

  • Mon, August 31, 2026
    Post begins
    Dailies, transcodes, editor setup, footage organization, BTS selects, trailer selects.
  • Fri, September 4, 2026
    Editor selects / structure review
    Editor has the full series organized and can identify any missing material early.
  • Mon, September 7, 2026
    Labor Day
    I would not rely on approvals this day.
  • Fri, September 11, 2026
    Full editor's assembly due
    First assembly of all 20 episodes.
  • Fri, September 18, 2026
    Producer/director cut due
    Internal creative cut of the full series.
  • Fri, September 25, 2026
    Internal rough cut review
    Review 20 episodes, BTS, and trailer internally before agency/client submission.
  • Mon, September 28, 2026
    Agency/client review cut delivered
    Gives Digitas and Bob Evans time to review before the October 5 notes date.
  • Mon, October 5, 2026
    Digitas & Bob Evans notes on edit
    Agency/client notes returned.
  • Tue–Tue, October 6–13, 2026
    Edit revisions
    Better revision window than the original schedule.
  • Wed, October 14, 2026
    Revised cut review
    Internal review of revised cut before lock.
  • Fri, October 16, 2026
    Picture lock
    All 20 episodes, BTS, and trailer locked for finishing.
  • Mon, October 19, 2026
    Sound mix and color begin
    Sound, color, graphics, captions prep, end cards, supers, and brand/legal checks.
  • Fri, October 23, 2026
    First finished masters due internally
    Mixed and colored versions ready for internal review.
  • Mon–Fri, October 26–30, 2026
    QC / captions / exports / final fixes
    October 30 becomes an internal master/QC milestone, not the final delivery date. This is much healthier.
  • Mon–Wed, November 2–4, 2026
    Final agency/client review of finished masters
    Review the polished files, not rough exports.
  • Thu, November 5, 2026
    Final fixes / captions / platform versions
    Address any final technical, caption, end card, legal, or brand notes.
  • Fri, November 6, 2026
    Final approval package
    Delivery files, captions, thumbnails/key art pulls, BTS, trailer, and masters packaged.
  • Mon, November 9, 2026
    Delivery buffer
    Hold for upload issues, QC failures, caption fixes, file naming, or last-minute replacement exports.
  • Mon, November 16, 2026
    Final Delivery
    Final delivery of micro-drama, BTS, trailer, captions, and required versions.